Modular construction: a way of building more quickly using multiple modules or skids, which are constructed in a controlled environment and set and connected on-site.
Modular construction is a well-established method in many industries; however, certain applications and benefits are not always fully understood in the refining and petrochemical industries. Modular refinery construction offers equivalent standards and significantly greater freedom and flexibility to a project compared to conventional, stick-built construction. Commonly discussed benefits of modular construction include decreased equipment capital expenditures and labor costs and streamlined project timelines. Safety and quality are two less frequently examined benefit areas that warrant a closer look.
Introduction to safety focus
Safety is a top priority in the construction industry and with good reason. According to the U.S. Bureau of Labor Statistics, there were 5,250 work-related fatal injuries in the private industry sector in 2018. Of those, 1,008 (19.2 percent) were in construction. These statistics indicate that nearly one in five private industry sector worker deaths occur in the construction industry.
The Occupational Safety and Health Administration (OSHA) has termed the leading causes of workplace deaths in the private construction industry sector as the "Fatal Four." They include falls, being struck by an object, electrocutions, and caught-in or caught-between incidents. When combined, these types of accidents were responsible for more than half (58.6 percent) or 591 construction worker deaths in 2018.
By integrating more modular components into construction projects, the refining and petrochemical industries could lower the occurrence of injuries and fatalities.
Controlled environment
Another key aspect of modularized construction is greater control of climate and weather variables. A traditional construction site is an ever-changing environment and mitigating hazards is an ever-moving target. In a shop setting, where modular components are typically built, there are many opportunities to implement hazard controls.
A permanent workshop facility garners benefits that range from additional training time for full-time employees to greater management of construction safety variables. On a traditional construction site, PPE is heavily relied upon to protect employees. In a shop environment, the use of PPE is still critical, but there are other hazard control methods such as hazard elimination or substitution that can be employed. For example, a shop welder can use different welding procedures or fume extractors to mitigate hazards when welding on exotic metals; this is often not possible on a construction site.
Another benefit of modularized construction is that worker safety and project schedules are far less likely to be impacted by weather. Traditional construction sites can experience weather events and extremes that increase risk and delay work. Workers are challenged by wet, icy or slippery conditions on ladders, scaffolding and lifts, and while using vehicles and equipment. Building in a controlled setting keeps workspace conditions predictable and schedules on track.
Skilled labor
A well-known fact in the construction industry is that short service employees (SSEs) suffer the highest rates of fatalities and severe injuries. Over the course of a decade, approximately two-thirds of fatalities occurred within the first year of service, and about one-third of fatalities occurred within the first three months of a new assignment. These statistics drive an effort in the construction industry to develop a long-term, skilled workforce. This approach is complicated by the temporary and often remote locations of construction projects.
A permanent shop operation runs with an established team that is experienced and specialized. After modular components are shipped from the module yard, a highly trained construction and commissioning team can accompany the equipment to oversee all aspects of installation through to startup.
Modular construction also minimizes the variability of finding skilled labor based on a project's location. Results from the U.S. Chamber of Commerce Commercial Construction Index for the third quarter of 2020 revealed that most contractors (83 percent) continue to report moderate to high levels of difficulty finding skilled workers, and more than one in three (36 percent) of those contractors also reported turning down work due to skilled labor shortages. An interesting accompanying data point from the U.S. Bureau of Labor Statistics is that the number of job openings in the construction industry over the past decade continues to increase year over year, further validating the labor shortage faced by this industry (FIG 2).
Vertical structures and fall prevention
Falls are the No. 1 cause of construction fatalities and account for one-third of all on-the-job deaths in the U.S. Maximizing the work done at ground level has a big impact on worker safety. A modular construction approach for tall vertical structures means structures can be built horizontally in a controlled shop environment (FIG 4). By eliminating or reducing the use of ladders and scaffolding for these types of builds, the contractor automatically lowers the risk of falls in the workplace.
Safety metrics
Total Recordable Incident Rate (TRIR) is the industry standard used to gauge a company's safety performance. The industry standard TRIR for oil and gas pipeline-related structures construction is 0.7, which equates to one OSHA recordable injury for every 285,000 hours worked. This number is even higher for heavy and civil engineering construction.
Shifting the work to a controlled environment reduces this statistic (FIG 3). For example, at Chemex Global Inc., the fabrication team achieved more than 1 million hours worked without an OSHA recordable injury in 2020. Additionally, the modular equipment construction process is often quicker than traditional, on-site construction, requiring fewer man-hours. FIG 3 shows the incremental time per discipline it takes to complete a task on-site versus in a controlled environment. For each one of the disciplines identified, greater than 75 percent of the work can be shifted from the construction site to the modular staging yard.
Continuous improvement
Possibly the most important safety benefit in modular construction is that working in a controlled environment fosters continuous improvement. Repeated processes and procedures create workflows that make it simpler to analyze and identify potential hazards as well as opportunities to improve methods and schedules.
In a modular construction operation, workers are proficient in their areas worked and understand the areas of caution. Skilled workers create assembly-line-like processes that reduce the likelihood of being struck by machinery, equipment or other objects. A permanent operation also instills a deep-rooted safety culture that starts from a worker's first day on the job and builds continuously over his or her long-term career.
Introduction to quality focus
Safety is just one half of the safety and quality benefit discussion. In a design-build operation, a focus on quality can also be embedded in all phases of a modular construction project from engineering and design to fabrication and turnover.
Total quality management
In a modular construction environment, an integrated approach can easily be used to improve the quality of deliverables. Total quality management (TQM) is a simple concept that involves training staff in all areas of quality inspection. A typical modular structure in the refining or petrochemical industry has the following construction disciplines: structural steel, piping, mechanical, instrumentation and electrical, and coatings. A controlled environment allows for real-time inspection of all these disciplines. Inspectors trained in the TQM approach can resolve issues before the equipment is shipped to the worksite.
With traditional stick-built construction, numerous dynamics influence the effectiveness of a quality management program. Many of the TQM system barriers are the same factors that impact safety. But there are other considerations as well. On-site construction projects differ greatly -- locations vary, as does work volume and intensity; the labor force is temporary (SSEs, key supervisors, quality personnel); projects are subject to delay; and the supply chain is extensive.
Internal quality auditing
Research from the Construction Industry Institute (CII) estimated annual losses due to rework in industrial construction at $15 billion. CII further estimated rework could be as much as 12 percent of the total project cost. Installing work incorrectly is an ongoing challenge and clearly points to a lack of training for those doing the work, but also for those inspecting the work. Quality assurance (QA) is the last line of defense for construction projects and these rework numbers illustrate the challenges of traditional construction methods.
A robust QA program brings effective solutions that eliminate the need for rework. When work is primarily shifted to a shop setting, the fabrication and construction processes (and teams) become standardized and present the opportunity to perform internal quality audits. A modular construction company can employ a formal quality audit plan that includes an audit schedule, corrective and preventive actions, findings and issue resolutions, and audit reports. In practice, management reviews audit findings and assesses overall effectiveness for the quality program. This ensures quality is being effectively implemented and that the services being performed match or exceed the project's quality requirements.
Typically, quality audits are performed at approximately 30 percent, 60 percent and 90 percent of a project's completion status when duration is a year or longer and appropriate in size and shape. With a formal quality program, all audits can be systematically recorded and reviewed with project managers. Appropriate personnel can be notified when findings or observations are logged. This can ensure responsibility is assigned for determining, documenting, and implementing appropriate and corrective actions. Follow-up reviews can also be conducted to verify and record the effectiveness of any corrective actions.
Factory accepted testing
Factory accepted testing (FAT) is a process that involves the testing of equipment and its capabilities at the fabricator's facility to verify it is operating in accordance with design specifications. FATs are typically performed on complex equipment, equipment with novel technology, and equipment that will experience either extensive transportation or complicated installation (i.e., at a grassroot site).
Modular construction is largely performed inside a facility meaning that all fabrication can be subject to extensive FAT; this type of testing protocol is not possible with stick-built projects. FATs provide a primary advantage so fabricators and vendors can prevent failed equipment returns at the project site, especially helpful when projects are located overseas.
Testing equipment in a controlled factory setting offers the following benefits to a project before shipping:
- Ability to identify incomplete or incorrectly installed components
- Better accessibility to testing materials
- Full access to required utilities
- Validation of equipment sizes/specs
- Highly trained staff that can support testing trials
- Controlled environment that does not impact test results
Conclusion
In summary, for refinery construction, modularization integration brings significant safety and quality advantages to projects when compared to stick-built construction. When safety is considered, there are key advantages of working in a controlled shop environment versus a changing field site. In the shop, key fabrication activities typically take place under a roof in a regulated climate. Modular construction creates the opportunity for all equipment to be fabricated and transported horizontally, reducing the need to work from significant heights. Naturally, safety is also improved through a permanent workforce, who statistically are more skilled and subject to consistent training and continuous improvement programs over a long period of time, unlike the temporary nature of a project construction site.
While cost and time savings will always be prevalent in the modular construction debate in the refining and petrochemical industries, there is reason for an even deeper and stronger discussion to be had when layering in the benefits of safety and quality.
To read a full version of this article with references, visit www.chemexglobal.com/news.
For more information about Chemex Global, visit www.chemexglobal.com or call (346) 388-6100.